Series I

Elementary School
- Replace classroom ceilings, lighting, unit ventilators, and flooring
- Replace corridor ceilings, lighting, and unit heaters
- Replace boiler system and fire alarm/public address (PA) systems
- Install kitchen hood system
- Complete asbestos abatement
- Revise and improve secure entry
- Update classroom furnishings and equipment
High School/Middle School
- Replace and expand drives and parking lots
Stanwood Learning Center
- Replace the current steam boiler with RTUs
Series II

Elementary School
- Add two new classrooms
- Remodel the existing building connection area
- Provide classroom furnishings and equipment for new classrooms
High School/Middle School
- Add four classrooms
- Add four restrooms
- Construct a new High School/Middle School office with secure entry
- Add a classroom to the Media Center
- Provide classroom furnishings and equipment for new classrooms
- Provide office furniture and furnishings
Series III - In Progress
Elementary School
- Replace windows, doors, and frames
- Install new gym bleachers
- Install new corridor flooring
- Upgrade restrooms
- Add an ADA-accessible ramp
- Complete painting related to remodeling
- Replace mechanical equipment and controls
High School/Middle School
- No Work
Series IV - Planning Stage
Elementary School
- Replace door hardware
- Replace restroom toilet partitions
- Replace chiller
- Install fume hoods in science classrooms
- Install new mechanical equipment controls
- Install a new water softener
- Update the public address (PA) system
- Provide loose equipment and furnishings, including tables, chairs, and associated classroom equipment
High School/Middle School
- No Work
Series V

Elementary School
- Loose equipment and furnishings, including tables, chairs, and associated classroom equipment
- Improve site drainage on the playground
High School/Middle School
- Improve drainage at the baseball field and track
- Improve parking lot lighting
- Replace stadium bleachers
The August 2020 Morley Stanwood bond authorized the district to borrow funds through voter-approved bonds to modernize facilities, improve safety, upgrade technology, and enhance school sites, funded through a property tax millage structured to maintain the district’s existing tax rate, and structured in multiple series to allow projects to be completed in phases over several years.